Old Bridge Road Project
Posted on Apr 18th, 2012
Day Work
Night Work
Week of April 23, 2012
1. Complete curbs, walks and aprons between 113+00 to 127+00 (Old Bridge Lane to 800’ east of Westridge Drive.)
2. Begin backfill of curbs, walks and aprons same as above.
3. Seed and mulch 103+75 to 112+50 (Just east of Titania Way to Old Bridge Lane)
4. Begin Earthwork 133+50 to 137+00 (Springwood Drive to 300’ west of Smoketown Road)
5. Complete Storm Sewer Road Crossing 136+50(350’ west of Smoketown Road)
6. Complete UD-4 installation 113+00 to 127+00(Old Bridge Lane to 800’ east of Westridge Drive.)
7. Complete Storm Sewer Road Crossing 145+00 to 148+00(400’ east of Smoketown to 700’ east of Smoketown Road)
Road/Direction: Old Bridge Road, Rte 641 Eastbound lane
Where: From Old Bridge Lane to 600’ west of Springwood Drive
When: 4/17-20/12, 9:00 A.M. TO 4:00 P.M.
What: Eastboind lane right lane closure
Why: curb and handicap ramp upgrades
Night Work
Road/Direction: Old Bridge Road, Rte 641 Westbound lane
Where: From Springwood Dr. to Westridge Dr.
When: 4/17-18/12, 7:00 P.M. TO 6:00 A.M.
What: Westbound Left Turn Lane
Why: Storm Sewer Crossing
Week of April 23, 2012
1. Complete curbs, walks and aprons between 113+00 to 127+00 (Old Bridge Lane to 800’ east of Westridge Drive.)
2. Begin backfill of curbs, walks and aprons same as above.
3. Seed and mulch 103+75 to 112+50 (Just east of Titania Way to Old Bridge Lane)
4. Begin Earthwork 133+50 to 137+00 (Springwood Drive to 300’ west of Smoketown Road)
5. Complete Storm Sewer Road Crossing 136+50(350’ west of Smoketown Road)
6. Complete UD-4 installation 113+00 to 127+00(Old Bridge Lane to 800’ east of Westridge Drive.)
7. Complete Storm Sewer Road Crossing 145+00 to 148+00(400’ east of Smoketown to 700’ east of Smoketown Road)